Record Modeling
Our objective is to maintain models with current construction changes and to use those models to produce final record documents (As-Builts). These are provided to the Appointing Party or local municipality upon completion of the deliverable in the format agreed upon in the BIM Execution Plan.
| Potential Value: |
|---|
The Design Team updates models periodically to reflect revisions (Bulletins, ASIs, Change Orders). The revised model and contract documents are transferred to the Construction Manager concurrently.
Field changes and RFIs are tracked by the CM team on as-built drawings weekly. These "red-lines" are incorporated into the fabrication models by the Construction Team/Subcontractors on a monthly basis.
At project completion, the Construction Team verifies that models contain all applicable RFIs and changes. Aggregate As-Built models are submitted to the owner according to project requirements.